Centurion 8m Pool Project

FINISHED CENTURION 8M POOL

 

DAY 1

Excavation. 


DAY 2

Place the fibreglass pool shell back and fill in with water. 


DAY 3

Saturday afternoon 4 pm.
Pool is full of water.
Concrete surrounds ready for tiling.
Steel and concrete. build swimming pool


DAY 4 

Pump, filter, light & electrical.

Cleaning of the pool. 


DAY 5

Finished concrete.
Pump filter is working. 
Customer to do the pump-house and paving later but already can swim.
*START TO FINISH 5 DAYS*

DAY 6


DAY 7


FULLY FINISHED

 

 